AACE International AACE-PSP Test Duration Spare time can be taken full use of for better practice, AACE International AACE-PSP Test Duration Also if you want to purchase the other exam dumps, we will give you big discount as old customers, AACE International AACE-PSP Test Duration At the same time, the experts also spent a lot of effort to study the needs of consumers, and committed to creating the best scientific model for users, The goal of our AACE-PSP latest exam guide is prompting you to challenge your limitations.

Outside-in thinking complements any approach your teams may https://www.lead2passed.com/AACE-International/new-planning-scheduling-professional-psp-exam-dumps-10118.html be taking to the actual implementation of software, but it changes how you measure success, You should read thisinformation to understand what's involved with encrypting Real AACE-PSP Dumps your device, including keeping the device plugged in during the encryption process and the password requirements.

Download AACE-PSP Exam Dumps

Alex took an interest in computers at a young AACE-PSP Updated Demo age, In this section we cover the core system technology in Ubuntu and problems that can crop up when using it, Emmett Test AACE-PSP Duration is also the author of a number of books on certification and operating systems.

Spare time can be taken full use of for better practice, Test AACE-PSP Duration Also if you want to purchase the other exam dumps, we will give you big discount as old customers, At the same time, the experts also spent a lot of Test AACE-PSP Duration effort to study the needs of consumers, and committed to creating the best scientific model for users.

AACE-PSP latest prep torrent & AACE-PSP sure test guide

The goal of our AACE-PSP latest exam guide is prompting you to challenge your limitations, Braindumps - Readymade Solution for a Fabulous Success, They have built a clear knowledge frame in their minds before they begin to compile the AACE-PSP actual test guide.

So DUMPSSURE is offering you to get excellent marks, We believe strongly that you can make it with our help of materials and services, and with your adamant confidence and our reliable AACE-PSP latest torrent you can stand out.

However, you should go through our AACE-PSP practice test software multiple times and use PDF dumps as well so you can achieve the desired results, Formatted questions just like on the real exam!

Whenever and wherever you want, you have access to the AACE-PSP pass-sure materials: Planning & Scheduling Professional (PSP) Exam by using your phone or your computer, After all, the pdf dumps have some limits for the people who want to study with high efficiency.

Download Planning & Scheduling Professional (PSP) Exam Exam Dumps

NEW QUESTION 28
Scenario:
The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.
AACE-PSP-c0df806648f9eec02403a7cba858f0ff.jpg
PSP Activities Table
Scope Known about Rock-Filled Dam Project:
The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing "no differing sit conditions" and "no damage for delay" clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.
Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the
"normal" schedule and $3,200 for the "crashed" schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor's operations by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.
The following table lists work activities as planned by the contractor.
AACE-PSP-2da6ab07c8e9fce8b7b70ad3366a59bd.jpg
Theoretically construct a summary activity for only those activities with a finish-to-start relationship for Activities 8001 through 10001. Using the "normal" schedule, what is the cost of this hammock?

  • A. $552,000.
  • B. $524,000.
  • C. $307,000.
  • D. $420,000.

Answer: A

 

NEW QUESTION 29
The work breakdown structure is used to organize

  • A. "Smart activity ID codes" representing similar items of scheduled work
  • B. Similar activity coding of schedule activities
  • C. The chart of accounts
  • D. The smallest defined work packet

Answer: D

 

NEW QUESTION 30
In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?
AACE-PSP-2da6ab07c8e9fce8b7b70ad3366a59bd.jpg

  • A. 2004.
  • B. 4001, 5001 and 6001.
  • C. 2003 and 7001.
  • D. 4001 and 5001.

Answer: D

 

NEW QUESTION 31
Which statement is true?

  • A. Where compensability cannot be established, excusability is assumed.
  • B. Where compensability cannot be established, excusability is a given.
  • C. Where compensability can be established, excusability is assumed.
  • D. Where compensability can be established, excusabltity cannot be assumed.

Answer: A

 